Budget Tracker (EVM)


Phase: Monitoring and controlling | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Budget Tracker uses Earned Value Management (EVM) to answer: are we spending more than planned for the work done, and are we behind schedule? It then forecasts the final cost.

Think of it like: You planned to paint 4 rooms for ₹40,000 in 4 days. After 2 days you have painted 1.5 rooms (earned ₹15,000) but spent ₹18,000. You are over budget and behind schedule.


When is it created?

Weekly during the project

Who prepares it?

Project Manager

Who approves or uses it?

Reviewed with Delivery Head fortnightly

What happens next?

Red status is escalated and a recovery plan agreed


How it connects to other documents

  1. Planned value comes from the Budget and Schedule.
  2. Actual cost comes from Timesheets and invoices.
  3. Thresholds come from the Project Management Plan.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Weekly earned value analysis against the budget at completion (BAC) of ₹4,58,000. Indices are used unrounded in forecasts.

Item


Detail


Document no.

WEB-2026-01/EVM

Version

1.0

Date

30 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Monitoring and controlling

Status

Red


Item


Detail


Budget at completion (BAC)

₹4,58,000

Cost baseline (BAC + contingency)

₹5,03,800

Cost status

Red

Schedule status

Green


1. Weekly trend (cumulative, ₹)

Week ending


PV


EV


AC


CV


SV


CPI


SPI


9 Oct (W1)

28,000

28,000

29,000

−1,000

0

0.966

1.000

16 Oct (W2)

60,000

58,000

63,000

−5,000

−2,000

0.921

0.967

23 Oct (W3)

1,10,000

1,06,000

1,18,000

−12,000

−4,000

0.898

0.964

30 Oct (W4)

1,70,600

1,65,000

1,82,000

−17,000

−5,600

0.907

0.967


2. Forecast at week 4

Measure


Formula


Value


Estimate at completion (EAC)

BAC ÷ CPI = 4,58,000 ÷ 0.9066

₹5,05,188

Estimate to complete (ETC)

EAC − AC

₹3,23,188

Variance at completion (VAC)

BAC − EAC

−₹47,188

To-complete performance index (TCPI)

(BAC − EV) ÷ (BAC − AC)

1.062

Contingency available


₹45,800

Forecast vs cost baseline

EAC − ₹5,03,800

₹1,388 over


3. Actual cost by category to date (₹)

Category


Planned


Actual


Variance


Labour

1,46,000

1,64,000

−18,000

Non-labour

24,600

18,000

+6,600

Total

1,70,600

1,82,000

−11,400


Note: Why Red: the forecast (₹5,05,188) exceeds the cost baseline (₹5,03,800), meaning the whole contingency would be used and more. The non-labour saving is only timing (hosting bought in week 5), so the real cause is the designer's 20 extra hours. To recover, remaining work must run at a CPI of 1.06 (TCPI). Escalated to the Delivery Head on 30 Oct.


4. Recovery actions

  1. Freeze designs: any further visual change goes through a billable change request.
  2. Cap PM client-call time at 2 hours per week; move content chasing to email.
  3. Use the approved CR-001 (₹12,000) to cover part of the design overrun in margin terms.
  4. Re-forecast weekly; if CPI stays below 0.95 by week 6, request management reserve.


WEB-2026-01/EVM · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. PV = planned work value, EV = value of work done, AC = actual cost.
  2. CPI = EV ÷ AC; SPI = EV ÷ PV. Below 1.0 is bad.
  3. EAC = BAC ÷ CPI forecasts the final cost if nothing changes.


Common mistakes to avoid

  1. Comparing only budget vs actual, without earned value.
  2. Using rounded CPI in forecasts.
  3. Waiting until the end to act on a Red status.


Next lesson: 32. Invoice and Payment Tracker