Phase: Monitoring and controlling | Audience: Internal | Project: WEB-2026-01 Corporate Website Development
In simple words: The Budget Tracker uses Earned Value Management (EVM) to answer: are we spending more than planned for the work done, and are we behind schedule? It then forecasts the final cost.
Think of it like: You planned to paint 4 rooms for ₹40,000 in 4 days. After 2 days you have painted 1.5 rooms (earned ₹15,000) but spent ₹18,000. You are over budget and behind schedule.
When is it created? | Weekly during the project |
Who prepares it? | Project Manager |
Who approves or uses it? | Reviewed with Delivery Head fortnightly |
What happens next? | Red status is escalated and a recovery plan agreed |
Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.
Issued by: [Your Company] Technologies Pvt. Ltd.
Purpose: Weekly earned value analysis against the budget at completion (BAC) of ₹4,58,000. Indices are used unrounded in forecasts.
Item | Detail |
Document no. | WEB-2026-01/EVM |
Version | 1.0 |
Date | 30 Oct 2026 |
Owner | Project Manager |
Audience | Internal |
Phase | Monitoring and controlling |
Status | Red |
Item | Detail |
Budget at completion (BAC) | ₹4,58,000 |
Cost baseline (BAC + contingency) | ₹5,03,800 |
Cost status | Red |
Schedule status | Green |
Week ending | PV | EV | AC | CV | SV | CPI | SPI |
9 Oct (W1) | 28,000 | 28,000 | 29,000 | −1,000 | 0 | 0.966 | 1.000 |
16 Oct (W2) | 60,000 | 58,000 | 63,000 | −5,000 | −2,000 | 0.921 | 0.967 |
23 Oct (W3) | 1,10,000 | 1,06,000 | 1,18,000 | −12,000 | −4,000 | 0.898 | 0.964 |
30 Oct (W4) | 1,70,600 | 1,65,000 | 1,82,000 | −17,000 | −5,600 | 0.907 | 0.967 |
Measure | Formula | Value |
Estimate at completion (EAC) | BAC ÷ CPI = 4,58,000 ÷ 0.9066 | ₹5,05,188 |
Estimate to complete (ETC) | EAC − AC | ₹3,23,188 |
Variance at completion (VAC) | BAC − EAC | −₹47,188 |
To-complete performance index (TCPI) | (BAC − EV) ÷ (BAC − AC) | 1.062 |
Contingency available | ₹45,800 | |
Forecast vs cost baseline | EAC − ₹5,03,800 | ₹1,388 over |
Category | Planned | Actual | Variance |
Labour | 1,46,000 | 1,64,000 | −18,000 |
Non-labour | 24,600 | 18,000 | +6,600 |
Total | 1,70,600 | 1,82,000 | −11,400 |
Note: Why Red: the forecast (₹5,05,188) exceeds the cost baseline (₹5,03,800), meaning the whole contingency would be used and more. The non-labour saving is only timing (hosting bought in week 5), so the real cause is the designer's 20 extra hours. To recover, remaining work must run at a CPI of 1.06 (TCPI). Escalated to the Delivery Head on 30 Oct.
WEB-2026-01/EVM · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.