Issue Log


Phase: Execution | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Issue Log records problems that have already happened, their impact, who is fixing them and by when.

Think of it like: On a trip, the train is cancelled. That is no longer a risk; it is an issue. You note it and decide to take a bus.


When is it created?

Execution, updated whenever an issue arises

Who prepares it?

Project Manager

Who approves or uses it?

Internal; serious issues escalated

What happens next?

Issues are tracked until resolved


How it connects to other documents

  1. Many issues start as risks in the Risk Register.
  2. Serious ones appear in the Weekly Status Report.
  3. Lessons from them go into the Lessons Learned Register.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Problems that have already happened, their impact, and the action to resolve them. A risk that occurs becomes an issue.


Item


Detail


Document no.

WEB-2026-01/IL

Version

1.0

Date

30 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Execution


1. Log

ID


Raised


Issue


Impact


Priority


Owner


Action


Target


Status


I-01

9 Oct

Logo supplied only as low-resolution JPG

Blurry logo on high-resolution screens

Medium

Designer

Requested vector file from client's agency

12 Oct

Resolved

I-02

16 Oct

Content for 4 services pages not received (risk R3)

Content upload in week 7 at risk

High

PM

Escalated to Head of Marketing; new date 6 Nov; placeholder text used meanwhile

6 Nov

Open

I-03

26 Oct

MD asked for a new home page layout in round 2 (risk R1)

20 extra designer hours; cost overrun

High

Designer

Absorbed within round 2 to protect sign-off date; lesson recorded

30 Oct

Resolved

I-04

28 Oct

Temporary staging server blocks outgoing email

Contact form cannot be tested

Medium

Backend

Switch to transactional email service early

13 Nov

Open

I-05

22 Oct

Designer on unplanned leave for 1 day

Inner page designs 1 day late

Low

PM

Designer worked Saturday 24 Oct

24 Oct

Resolved


Note: Risk vs issue: a risk is something that might happen (in the Risk Register); an issue has already happened and needs action now. I-02 and I-03 started life as risks R3 and R1.


WEB-2026-01/IL · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Risk = might happen; issue = has happened.
  2. Every issue needs an owner, an action and a target date.
  3. Escalate early when an issue threatens a milestone.


Common mistakes to avoid

  1. Confusing risks and issues.
  2. Leaving issues 'open' with no action.
  3. Hiding issues from the sponsor.