Change Management Plan


Phase: Planning | Audience: Shared | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Change Management Plan explains how any change to scope, time or cost is requested, assessed, approved and recorded. It turns 'can you just add...' into a clear process.

Think of it like: In a restaurant, if you ask to change your order after the chef has started, the waiter tells you the extra cost and time before the kitchen does it.


When is it created?

Planning (9 Oct 2026)

Who prepares it?

Project Manager

Who approves or uses it?

Agreed with the client

What happens next?

Used for every change request during execution


How it connects to other documents

  1. Rates come from the Commercial Proposal rate card.
  2. Each request is recorded in the Change Request Log.
  3. Approved changes update the Scope, Schedule and Budget.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: How requests to change scope, schedule or cost are raised, assessed, approved and recorded.


Item


Detail


Document no.

WEB-2026-01/CHP

Version

1.0

Date

9 Oct 2026

Owner

Project Manager

Audience

Shared with client

Phase

Planning

Status

Approved


1. What counts as a change

Situation


Change?


How it is handled


New page, feature or integration

Yes

Change request, billable

Third or later design revision round

Yes

Change request, ₹18,000 per round

Something built differently from approved design

No, a defect

Fixed free under warranty

Wording or image swap before content freeze

No

Included

Client delay moving a milestone

Yes, schedule change

Logged; dates move day for day


2. Process

  1. Anyone raises a request using the Change Request Form.
  2. PM logs it in the Change Request Log with a CR number.
  3. Team assesses cost, schedule, quality and risk impact within 2 working days.
  4. Approver decides: approve, reject or defer.
  5. If approved, PM updates the scope, schedule and budget baselines and version numbers.
  6. PM communicates the decision to the team and client in writing.


3. Approval authority

Type of change


Approver


Any billable change to the client

Client Head of Marketing (written)

Internal cost using contingency up to ₹10,000

Project Manager

Internal cost above ₹10,000 or using management reserve

Delivery Head

Change to go-live date

Client Head of Marketing and Delivery Head


4. Pricing

Changes are priced from the Commercial Proposal rate card: ₹1,200 per hour, ₹12,000 per additional page, ₹18,000 per extra design round, plus GST.

WEB-2026-01/CHP · v1.0 · Shared with client. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. A defect (built wrong) is not a change; it is fixed free.
  2. Every change is assessed for cost, time, quality and risk.
  3. Only named people can approve changes.


Common mistakes to avoid

  1. Accepting 'small' changes verbally.
  2. Not updating baselines after approval.
  3. Letting the team make changes directly for the client.


Next lesson: 24. Minutes of Meeting (MoM)