Weekly Status Report


Phase: Monitoring and controlling | Audience: Client-facing | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Weekly Status Report tells the client where the project stands: overall health (Red/Amber/Green), what was done, what is next, milestones, actions needed from them and top risks.

Think of it like: A school progress report: grades, what went well, what needs attention, and what parents should do.


When is it created?

Every Friday during the project

Who prepares it?

Project Manager

Who approves or uses it?

Sent to client sponsor and Delivery Head

What happens next?

Discussed in the weekly call


How it connects to other documents

  1. Data comes from the Schedule, Risk Register and Issue Log.
  2. Client actions come from Minutes of Meeting.
  3. Schedule of reports is set by the Communication Plan.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Progress for the week ending 30 Oct 2026, sent to the client sponsor.


Item


Detail


Document no.

WEB-2026-01/WSR-04

Version

1.0

Date

30 Oct 2026

Owner

Project Manager

Audience

Client-facing

Phase

Monitoring and controlling


Item


Detail


Overall

Amber

Schedule

Amber

Scope

Green

Quality

Green

Work complete

36% (planned 37%)


1. Summary

Designs for all seven page types were approved on 30 Oct, on schedule. The project is marked Amber because content for the four services pages has not yet arrived; if it is not received by 6 Nov, content upload in week 7 and the go-live date will be at risk.


2. Completed this week

  1. Round 2 design revisions delivered and approved.
  2. Design sign-off form signed (milestone D2).
  3. Staging environment and code repository set up.


3. Planned next week

  1. Start theme development and CMS configuration.
  2. Build the contact form on staging.
  3. Assess change requests raised by your team.


4. Milestones

Milestone


Planned


Forecast


Status


Kickoff

5 Oct

5 Oct

Achieved

Sitemap approved

14 Oct

14 Oct

Achieved

Design sign-off

30 Oct

30 Oct

Achieved

Staging site ready

27 Nov

27 Nov

Amber

UAT sign-off

4 Dec

4 Dec

Green

Go-live

9 Dec

9 Dec

Green


5. Actions needed from you

Action


Owner


Due


Status


Content for four services pages

Marketing Executive

6 Nov

Overdue

Pay invoice INV-2026-118 (M2)

Finance

14 Nov

Due


6. Top risks

Risk


Impact


What we are doing


Late services content

Launch delay

Using placeholder text so development continues

New requests during build

Scope and cost growth

Routing through change requests


WEB-2026-01/WSR-04 · v1.0 · Client-facing. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Be honest: Amber early is better than Red late.
  2. Always list what you need from the client.
  3. Keep it short enough to read in 2 minutes.


Common mistakes to avoid

  1. Reporting everything Green until it is too late.
  2. Only listing activities, not results.
  3. Sharing internal cost details with the client.


Next lesson: 31. Budget Tracker (EVM)