Phase: Monitoring and controlling | Audience: Client-facing | Project: WEB-2026-01 Corporate Website Development
In simple words: The Weekly Status Report tells the client where the project stands: overall health (Red/Amber/Green), what was done, what is next, milestones, actions needed from them and top risks.
Think of it like: A school progress report: grades, what went well, what needs attention, and what parents should do.
When is it created? | Every Friday during the project |
Who prepares it? | Project Manager |
Who approves or uses it? | Sent to client sponsor and Delivery Head |
What happens next? | Discussed in the weekly call |
Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.
Issued by: [Your Company] Technologies Pvt. Ltd.
Purpose: Progress for the week ending 30 Oct 2026, sent to the client sponsor.
Item | Detail |
Document no. | WEB-2026-01/WSR-04 |
Version | 1.0 |
Date | 30 Oct 2026 |
Owner | Project Manager |
Audience | Client-facing |
Phase | Monitoring and controlling |
Item | Detail |
Overall | Amber |
Schedule | Amber |
Scope | Green |
Quality | Green |
Work complete | 36% (planned 37%) |
Designs for all seven page types were approved on 30 Oct, on schedule. The project is marked Amber because content for the four services pages has not yet arrived; if it is not received by 6 Nov, content upload in week 7 and the go-live date will be at risk.
Milestone | Planned | Forecast | Status |
Kickoff | 5 Oct | 5 Oct | Achieved |
Sitemap approved | 14 Oct | 14 Oct | Achieved |
Design sign-off | 30 Oct | 30 Oct | Achieved |
Staging site ready | 27 Nov | 27 Nov | Amber |
UAT sign-off | 4 Dec | 4 Dec | Green |
Go-live | 9 Dec | 9 Dec | Green |
Action | Owner | Due | Status |
Content for four services pages | Marketing Executive | 6 Nov | Overdue |
Pay invoice INV-2026-118 (M2) | Finance | 14 Nov | Due |
Risk | Impact | What we are doing |
Late services content | Launch delay | Using placeholder text so development continues |
New requests during build | Scope and cost growth | Routing through change requests |
WEB-2026-01/WSR-04 · v1.0 · Client-facing. Bracketed items such as [Client Name] are placeholders.
Next lesson: 31. Budget Tracker (EVM)