Invoice and Payment Tracker


Phase: Monitoring and controlling | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Invoice and Payment Tracker records every invoice raised to the client, when it is due and whether it has been paid.

Think of it like: A landlord's rent register: which month's rent is billed, due and received.

When is it created?

Updated at every milestone and payment

Who prepares it?

Project Manager with finance

Who approves or uses it?

Internal

What happens next?

Follow up on overdue payments


How it connects to other documents

  1. Milestones come from the Commercial Proposal and SOW.
  2. Triggered by sign-off forms.
  3. Explains the gap in the Cash Flow Analysis.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Milestone invoices raised, due and received, including approved change requests.

Item


Detail


Document no.

WEB-2026-01/INV

Version

1.0

Date

30 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Monitoring and controlling


1. Invoices (amounts in ₹)

Milestone


Invoice no.


Date


Amount


GST


Total


Due


Received


Status


M1 Advance 30% + third-party

INV-2026-101

1 Oct

2,08,350

37,503

2,45,853

16 Oct

3 Oct

Paid

M2 Design approval 30%

INV-2026-118

30 Oct

1,66,350

29,943

1,96,293

14 Nov


Due

M3 UAT sign-off 30%


4 Dec

1,66,350

29,943

1,96,293

19 Dec


Planned

CR-001 Careers page


4 Dec

12,000

2,160

14,160

19 Dec


Planned

M4 Go-live 10%


11 Dec

55,450

9,981

65,431

26 Dec


Planned

Total



6,08,500

1,09,530

7,18,030





2. Summary (excluding GST, ₹)

Item


Amount


Contract value

5,96,500

Approved change requests

12,000

Total billable

6,08,500

Billed to date

3,74,700

Received to date

2,08,350

Outstanding (billed, not received)

1,66,350

Not yet billed

2,33,800


Note: The dashboard cash-flow view assumed M2 would be received in month 1. With M2 due on 14 Nov, the month 2 cash gap is wider than planned until it is paid. Follow up with client finance on 10 Nov.


WEB-2026-01/INV · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Invoice on the same day as the sign-off.
  2. Include approved change requests as billable.
  3. Track billed, received, outstanding and unbilled separately.


Common mistakes to avoid

  1. Forgetting to bill approved changes.
  2. Not following up before the due date.
  3. Mixing amounts with and without GST.


Next lesson: 33. UAT Test Cases