Procurement Plan


Phase: Planning | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Procurement Plan lists everything we need to buy (domain, hosting, licences, tools), from whom, in whose name, by when and at what cost.

Think of it like: A shopping list for a house move: boxes, van rental, new locks, with who pays, when you need them and whose name the rental is in.


When is it created?

Planning (9 Oct 2026)

Who prepares it?

Project Manager

Who approves or uses it?

PM for listed items; Delivery Head for anything else

What happens next?

Items are purchased and credentials stored safely


How it connects to other documents

  1. Costs match non-labour items in the Budget.
  2. Third-party items are priced at cost in the Commercial Proposal.
  3. Renewal dates are passed on in the Handover Document.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Third-party items to buy, from whom, in whose name, when, and how they are approved.


Item


Detail


Document no.

WEB-2026-01/PP

Version

1.0

Date

9 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Planning


1. Procurement list

Item


Specification


Registered to


Needed by


Cost (₹)


Status


Domain name

.com, 1 year, auto-renew off

Client

Week 1

1,000

Purchased

Project tools

Figma and Jira seats, 3 months

Our company

Week 1

9,000

Purchased

Stock images and icons

1-month subscription, perpetual licence for downloads

Client

Week 2

8,000

Purchased

Premium theme and plugin licences

Page builder, SEO, forms; 1 year

Client

Week 4

12,000

Purchased

Cloud hosting

2 vCPU, 4 GB RAM, Mumbai region, 12 months

Client

Week 5

18,000

Pending

Transactional email service

Form email delivery, 12 months

Client

Week 7

3,000

Planned

SSL certificate

Let's Encrypt, auto-renewing

Client

Week 10

0

Planned


2. Rules

  1. Items the client will own after handover are registered in the client's company name and email.
  2. Purchases over ₹10,000 need a comparison of at least two options, recorded in the Decision Log.
  3. The PM approves purchases listed here; anything not listed needs Delivery Head approval.
  4. All credentials are stored in the password manager and handed over at closure.
  5. Renewal dates are listed in the Handover Document so the client is not caught out.

Note: Hosting was planned for week 4 but moved to week 5 because staging ran on a temporary server. This is why actual non-labour spend at week 4 is lower than planned.


WEB-2026-01/PP · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Buy items the client will own in the client's name.
  2. Plan when each item is needed, not all on day one.
  3. Record renewal dates so the client is not surprised later.


Common mistakes to avoid

  1. Registering the client's domain in our company's name.
  2. Losing track of passwords for purchased services.
  3. Buying unlisted items without approval.


Next lesson: 23. Change Management Plan