Risk Register


Phase: Planning | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Risk Register lists things that might go wrong, how likely and how serious they are, what we will do about them, who owns them and how much money is kept aside.

Think of it like: Before an outdoor wedding you note: 'rain is possible, so book a tent'. The risk is rain; the response is the tent; the cost of the tent is your reserve.


When is it created?

Planning, reviewed every Monday

Who prepares it?

Project Manager with risk owners

Who approves or uses it?

Internal; top risks reported to sponsor

What happens next?

Risks that happen move to the Issue Log


How it connects to other documents

  1. Reserves add up to the ₹45,800 contingency in the Budget.
  2. Risks R1 and R3 later became issues I-03 and I-02 in the Issue Log.
  3. Top risks appear in the Weekly Status Report.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Identified risks with probability, impact, response and owner. Reviewed every Monday. Scores use a 1–5 scale; score = probability × impact.


Item


Detail


Document no.

WEB-2026-01/RR

Version

1.3

Date

30 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Planning


1. Register

ID


Risk (cause → effect)


P


I


Score


Response


Action


Owner


Reserve (₹)


Status


R1

Client requests a third design round → design effort and schedule overrun

3

3

9

Mitigate

Show designs to MD before sign-off; bill extra rounds via rate card

Designer

14,000

Open

R2

CMS or form integration problems → extra backend effort

2

4

8

Mitigate

Build and test form in week 4 on staging

Backend

12,750

Open

R3

Client content arrives late → developers idle, launch at risk

4

3

12

Mitigate

Content calendar; weekly reminder; use placeholder text to keep building

PM

11,000

Open

R4

Licence or hosting prices rise → higher non-labour cost

2

2

4

Accept

Buy annual licences at start

PM

8,050

Closed

R5

Diwali week reduces capacity → schedule slip

3

2

6

Avoid

Plan 60% capacity in week 6

PM

0

Monitoring

R6

Key developer unavailable → development delay

2

4

8

Mitigate

Code in Git; backup developer identified

Delivery Head

0

Open

R7

Client pays late → cash gap in month 2

3

3

9

Mitigate

Invoice on sign-off day; payment terms in SOW

PM

0

Open

R8

Informal requests via chat → scope creep

4

3

12

Avoid

All requests through change request form

PM

0

Open

R9

Delayed DNS or domain access → go-live delay

3

3

9

Mitigate

Access requested in week 1; test DNS change in week 9

Backend

0

Open

R10

Performance target missed → quality criterion fails

2

3

6

Mitigate

Image compression and caching from the start

Frontend

0

Open


Total contingency reserve







45,800



2. Scoring guide

Score


Rating


Action


12–25

High

Weekly action; report to sponsor

6–11

Amber

Monitor weekly; response plan ready

1–5

Green

Review monthly


Note: Update on 30 Oct: R1 partly happened (home design needed extra rework, logged as issue I-03). R4 closed after licences were bought at the quoted price.

WEB-2026-01/RR · v1.3 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Score = probability × impact; focus on the highest scores.
  2. Write risks as cause → effect.
  3. Every risk needs an owner and an action, not just a description.


Common mistakes to avoid

  1. Writing vague risks like 'project may be delayed'.
  2. Creating the register once and never reviewing it.
  3. No money set aside for likely risks.


Next lesson: 21. Quality and Test Plan