Phase: Pre-sales and initiation | Audience: Internal | Project: WEB-2026-01 Corporate Website Development
In simple words: The Stakeholder Register lists everyone who can affect or is affected by the project, what they care about, how much influence they have and how we will keep them engaged.
Think of it like: Planning a wedding, you note who must approve the menu (parents), who only needs an invitation (distant relatives), and who can cancel everything (whoever is paying).
When is it created? | Initiation, updated at every phase (6 Oct 2026) |
Who prepares it? | Project Manager |
Who approves or uses it? | Internal use; reviewed with the sponsor |
What happens next? | Feeds the Communication Plan and RACI |
Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.
Issued by: [Your Company] Technologies Pvt. Ltd.
Purpose: Everyone who affects or is affected by the project, what they care about and how we will engage them.
Item | Detail |
Document no. | WEB-2026-01/SR |
Version | 1.0 |
Date | 6 Oct 2026 |
Owner | Project Manager |
Audience | Internal |
Phase | Pre-sales and initiation |
ID | Stakeholder | Organisation | Role in project | Interest | Influence | Engagement strategy |
S1 | Head of Marketing | Client | Project sponsor; approves designs, UAT and payments | High | High | Manage closely: weekly call, milestone reviews |
S2 | Managing Director | Client | Final say on brand and look | Medium | High | Keep satisfied: show designs before sign-off |
S3 | Marketing Executive | Client | Day-to-day contact; supplies content; future site editor | High | Medium | Keep informed: daily email, training |
S4 | IT Administrator | Client | Domain, DNS and email settings | Low | Medium | Keep satisfied: give early notice of access needs |
S5 | Finance Team | Client | Processes invoices | Low | Medium | Monitor: send invoices with sign-off proof |
S6 | Delivery Head | Our company | Internal sponsor; approves budget changes | High | High | Manage closely: fortnightly budget review |
S7 | Project Manager | Our company | Plans, coordinates, reports | High | High | Owner of this register |
S8 | UI/UX Designer | Our company | Design deliverables | High | Medium | Daily stand-up |
S9 | Developers (frontend, backend) | Our company | Build and deploy | High | Medium | Daily stand-up |
S10 | QA Tester and Content Writer | Our company | Testing and copy | Medium | Low | Daily stand-up |
S11 | Hosting provider | Vendor | Server and uptime | Low | Low | Monitor: support ticket when needed |
S12 | Website visitors | Public | End users of the site | Medium | Low | Represented through usability and UAT checks |

Quadrant | Stakeholders | Approach |
High influence, high interest | Head of Marketing, Delivery Head, Project Manager | Manage closely |
High influence, lower interest | Managing Director, IT Administrator | Keep satisfied |
Lower influence, high interest | Marketing Executive, project team | Keep informed |
Lower influence, lower interest | Finance, hosting provider, visitors | Monitor |
Note: The Managing Director has high influence but is not in weekly calls. Show the homepage design to the MD before the design sign-off so a late objection does not cause a third revision round.
WEB-2026-01/SR · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.