Cash Flow Analysis


Cumulative project spend against client payments received, excluding GST. A project can be profitable and still run short of cash in the middle.

Cumulative spend vs payments received

Monthly position

Point in time

Spend (₹)

Received (₹)

Position (₹)

End of month 1 (M1 + M2 received)

1,70,600

3,74,700

+2,04,100

End of month 2 (no new payment)

3,93,750

3,74,700

−19,050

End of month 3 (M3 + M4 received)

4,58,000

5,96,500

+1,38,500

Cash gap: In month 2 spend runs ahead of payments by about ₹19,050, because development is the most expensive phase and the next payment (M3) only comes at UAT sign-off in week 9.

Payment milestones

Milestone

Trigger

Amount (₹)

Incl. GST (₹)

M1 Advance 30%

PO signed (includes ₹42,000 third-party)

2,08,350

2,45,853

M2 Design approval 30%

Design sign-off, week 4

1,66,350

1,96,293

M3 UAT sign-off 30%

UAT sign-off, week 9

1,66,350

1,96,293

M4 Go-live 10%

Launch and handover, week 10

55,450

65,431

Total


5,96,500

7,03,870

How a PM manages the gap

  1. Invoice on the same day as each sign-off.
  2. Agree the M3 invoice date with the client early.
  3. Follow up payments before they are due (see lesson 32, Invoice and Payment Tracker).
  4. Keep a 30% advance clause as standard.