Project Schedule (Gantt)


Phase: Planning | Audience: Shared | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Project Schedule shows every task with start and end dates, who does it and what it depends on. The Gantt chart is the visual version. The critical path shows the tasks that decide the finish date.

Think of it like: A wedding day timeline: hall decoration must finish before guests arrive; the photographer must arrive before the ceremony. Any delay in the key steps delays the whole event.


When is it created?

Planning (9 Oct 2026), updated weekly

Who prepares it?

Project Manager

Who approves or uses it?

Shared with and agreed by the client

What happens next?

Progress is tracked against it every week


How it connects to other documents

  1. Tasks come from the WBS.
  2. Milestones trigger payments in the Invoice Tracker.
  3. Progress against it gives SPI in the EVM tracker.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Task-level schedule with dates, dependencies and owners. This is the schedule baseline.


Item


Detail


Document no.

WEB-2026-01/SCH

Version

1.0

Date

9 Oct 2026

Owner

Project Manager

Audience

Shared with client

Phase

Planning

Status

Approved


1. Milestones

Milestone


Date


Linked payment


Kickoff

Mon 5 Oct 2026

M1 advance received

Sitemap approved

Wed 14 Oct 2026


Design sign-off

Fri 30 Oct 2026

M2 30%

Staging site ready

Fri 27 Nov 2026


UAT sign-off

Fri 4 Dec 2026

M3 30%

Go-live

Wed 9 Dec 2026


Handover complete

Fri 11 Dec 2026

M4 10%


2. Task schedule

WBS


Task


Start


Finish


Predecessor


Owner


1.1

Kickoff and charter

5 Oct

6 Oct


PM

1.2

Requirement study

5 Oct

9 Oct


PM

1.3

Sitemap and project plan

7 Oct

14 Oct

1.2

PM

2.1

Wireframes

12 Oct

16 Oct

1.2

Designer

2.2

Home page design

15 Oct

21 Oct

2.1

Designer

2.3

Inner page designs

19 Oct

26 Oct

2.2

Designer

2.4

Revisions and sign-off

26 Oct

30 Oct

2.3

Designer

3.1

Environment and staging

26 Oct

28 Oct

1.3

Backend

3.2

Theme development

2 Nov

20 Nov

2.4, 3.1

Frontend

3.3

CMS configuration

2 Nov

18 Nov

2.4, 3.1

Backend

3.4

Forms and analytics

16 Nov

20 Nov

3.3

Backend

3.5

Content upload and SEO

18 Nov

27 Nov

3.2, 3.3

Content

4.1

Test planning

16 Nov

20 Nov

1.3

QA

4.2

System testing

23 Nov

2 Dec

3.2, 4.1

QA

4.3

Bug fixing

25 Nov

3 Dec

4.2

Frontend

4.4

UAT

1 Dec

4 Dec

4.2

PM + client

5.1

Go-live deployment

7 Dec

9 Dec

4.4

Backend

5.2

Training and handover

9 Dec

11 Dec

5.1

PM

5.3

Hypercare

9 Dec

23 Dec

5.1

Backend


3. Critical path

1.2 → 2.1 → 2.2 → 2.3 → 2.4 → 3.2 → 4.2 → 4.4 → 5.1. Any delay to these tasks delays go-live. Design sign-off on 30 Oct is the most sensitive date because development cannot start without it.


Note: Diwali falls in week 6 (8 Nov). Developer availability that week is planned at 60%; theme development runs to 20 Nov to absorb this.


WEB-2026-01/SCH · v1.0 · Shared with client. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Know your critical path; protect those tasks first.
  2. Plan for holidays and reduced capacity (Diwali week here).
  3. Milestones linked to payments must be realistic.


Common mistakes to avoid

  1. Ignoring dependencies between tasks.
  2. No buffer before key dates like UAT.
  3. Not updating the schedule when reality changes.


Next lesson: 17. Project Budget (Cost Baseline)