Kickoff Meeting Deck


Phase: Pre-sales and initiation | Audience: Shared | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Kickoff Meeting Deck is the set of slides presented at the first joint meeting with the client and the team. It makes sure everyone starts with the same understanding of goals, scope, timeline and ways of working.

Think of it like: The first meeting with the wedding planner, family and vendors where everyone hears the same plan, dates and who to call.

When is it created?

Day one of the project (5 Oct 2026)

Who prepares it?

Project Manager

Who approves or uses it?

Presented to client and team

What happens next?

Minutes of Meeting are sent within 24 hours


How it connects to other documents

  1. Its content summarises the SOW, Schedule and Communication Plan.
  2. 'What we need from you' becomes action items in the Minutes of Meeting.
  3. Risks shown here come from the Risk Register.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Slides presented at the joint kickoff meeting with the client and project team.

Item


Detail


Document no.

WEB-2026-01/KOM

Version

1.0

Date

5 Oct 2026

Owner

Project Manager

Audience

Shared with client

Phase

Pre-sales and initiation


Slide 1: Corporate Website Development: project kickoff

[Client Name] Pvt. Ltd. and [Your Company] Technologies Pvt. Ltd.

5 October 2026 · Google Meet


Slide 2: Agenda

  1. Introductions
  2. Goals and scope
  3. Timeline and milestones
  4. Team and roles
  5. Ways of working
  6. What we need from you
  7. Risks
  8. Questions and next steps


Slide 3: What success looks like

  1. A site that works on every device
  2. Your team updates content without developers
  3. 30% more enquiries within 6 months
  4. Live by 9 December 2026


Slide 4: Scope

Included


Not included


10 pages, blog and portfolio

E-commerce and logins

Contact form with email alerts

CRM or ERP integration

Analytics and on-page SEO

Paid ads and social media

Training and 14-day support

Ongoing maintenance


Slide 5: Timeline

Phase


Dates


Milestone


Planning

5–14 Oct

Sitemap approved

Design

12–30 Oct

Design sign-off 30 Oct

Development

26 Oct–27 Nov

Staging link

Testing and UAT

16 Nov–4 Dec

UAT sign-off 4 Dec

Launch

7–11 Dec

Go-live 9 Dec


Slide 6: Team and roles

Client


Our team


Head of Marketing: sponsor and approvals

Project Manager: single point of contact

Marketing Executive: content and daily contact

Designer, two developers, QA, content writer

IT Administrator: domain and DNS

Delivery Head: escalation


Slide 7: Ways of working

  1. Weekly status call every Tuesday, 11:00
  2. Written status report every Friday
  3. Feedback on reviews within 3 working days
  4. Decisions confirmed in minutes within 24 hours
  5. Changes go through a written change request


Slide 8: What we need from you

Item


By


Logo files and brand guidelines

9 Oct

Domain and DNS access

9 Oct

Content for all pages

16 Oct

Portfolio images

16 Oct

UAT testers available

1–4 Dec


Slide 9: Risks we will watch together

  1. Late content delays development
  2. Extra design revision rounds
  3. New requests during the build
  4. Reduced availability during Diwali week


Slide 10: Next steps

  1. Share minutes and action items today
  2. Requirement workshop on 7 Oct
  3. Sitemap for approval by 14 Oct
  4. Wireframes from 12 Oct


WEB-2026-01/KOM · v1.0 · Shared with client. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Keep it to about 10 slides and 90 minutes.
  2. Always include what you need from the client, with dates.
  3. Explain the change process on day one to prevent scope creep.


Common mistakes to avoid

  1. Presenting only our side and not the client's responsibilities.
  2. No written minutes after the meeting.
  3. Hiding risks to look positive.


Next lesson: 13. Project Management Plan