Quality and Test Plan


Phase: Planning | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Quality and Test Plan defines what 'good quality' means for this website, how it will be tested, how serious each defect is and when testing can start and finish.

Think of it like: Before a restaurant opens, the owner decides the standards (food hot within 15 minutes, clean tables), tastes every dish, and does not open until serious problems are fixed.


When is it created?

Planning (12 Oct 2026)

Who prepares it?

QA Tester

Who approves or uses it?

Project Manager

What happens next?

Test cases are written and run; the client does UAT


How it connects to other documents

  1. Targets come from the RFP's non-functional requirements (speed, browsers, accessibility).
  2. Leads to the UAT Test Cases and UAT Sign-off.
  3. Exit criteria are checked in the Go-Live Checklist.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Quality targets for the website, the testing approach, defect rules and the criteria for moving between stages.


Item


Detail


Document no.

WEB-2026-01/QTP

Version

1.0

Date

12 Oct 2026

Owner

QA Tester

Audience

Internal

Phase

Planning

Status

Approved


1. Quality targets

Area


Target


How measured


Performance

Load under 3 s on 4G; mobile PageSpeed score 80 or more

Google PageSpeed Insights

Responsiveness

Correct layout at 360, 768, 1280 and 1920 px

Browser tools and real devices

Browsers

Latest two versions of Chrome, Safari, Edge, Firefox

Manual testing

Accessibility

WCAG 2.1 AA contrast, alt text, keyboard navigation

Contrast checker, keyboard test

Forms

Email reaches sales inbox within 1 minute

Test submissions

SEO

Unique title and description on every page; sitemap submitted

SEO plugin report

Defects at launch

Zero critical or high defects open

Jira defect board


2. Test types

Test


What


Who


When


Design review

Designs against requirements

PM, client

Week 3–4

Unit and developer testing

Each template and component

Developers

Weeks 5–8

System testing

All pages and functions

QA

Weeks 8–9

Cross-browser and device

Layouts and behaviour

QA

Week 8

Performance and accessibility

Speed and WCAG checks

QA

Week 9

User acceptance testing

Business scenarios

Client

1–4 Dec


3. Defect severity

Severity


Definition


Example


Fix time


Critical

Site or key function unusable

Contact form does not send

Same day

High

Major function wrong, no workaround

Menu broken on mobile

1 working day

Medium

Function works with a workaround

Gallery filter slow

3 working days

Low

Cosmetic

Spacing off by a few pixels

Before go-live if time allows


4. Entry and exit criteria

Stage


Entry


Exit


System testing

All pages on staging; content uploaded

All test cases run; no critical defects

UAT

System testing exit met; UAT script shared

All UAT cases passed; client sign-off

Go-live

UAT signed; go-live checklist ready

Smoke test passed on production


WEB-2026-01/QTP · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Quality targets must be measurable (under 3 seconds, PageSpeed 80+).
  2. Define defect severity before testing starts.
  3. Entry and exit criteria stop half-ready work moving forward.


Common mistakes to avoid

  1. Testing only on one browser or device.
  2. Arguing about severity during UAT because it was never defined.
  3. Launching with high-severity defects open.


Next lesson: 22. Procurement Plan