Phase: Pre-sales and initiation | Audience: Internal | Project: WEB-2026-01 Corporate Website Development
In simple words: The Project Charter is the internal document that officially starts the project. It names the Project Manager, states the objectives and budget, and says how much authority the PM has.
Think of it like: It is like an appointment letter for the project: 'This project exists, here is the goal, here is the money, and you are in charge.'
When is it created? | Start of the project (5 Oct 2026) |
Who prepares it? | Project Manager drafts it |
Who approves or uses it? | Project Sponsor (Delivery Head) |
What happens next? | Planning begins; the PM can now use company resources |
Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.
Issued by: [Your Company] Technologies Pvt. Ltd.
Purpose: Formally authorises the project, names the Project Manager and states the objectives, budget and authority limits.
Item | Detail |
Document no. | WEB-2026-01/PCH |
Version | 1.0 |
Date | 5 Oct 2026 |
Owner | Project Manager |
Audience | Internal |
Phase | Pre-sales and initiation |
Status | Approved |
[Client Name] has awarded us a fixed-price contract to build its new corporate website. Delivering on time and within budget protects a 15.5% gross margin and positions us for a follow-on maintenance contract and a Hindi-language phase 2.
# | Objective | Success measure |
1 | Deliver the agreed scope | All 7 SOW deliverables accepted by the client |
2 | Launch on time | Go-live on or before 9 Dec 2026 |
3 | Stay within budget | Final cost within cost baseline of ₹5,03,800 |
4 | Meet quality targets | No critical or high defects at launch; pages under 3 s on 4G |
5 | Satisfied client | Client satisfaction score of 4 or more out of 5 at closure |
In scope: 10-page responsive WordPress website, contact form, blog, portfolio, analytics, on-page SEO, hosting setup, training and 14-day support. Out of scope: e-commerce, logins, integrations beyond the contact form, marketing, and maintenance after support ends.
Milestone | Target date | Payment |
Kickoff | 5 Oct 2026 | M1 30% (advance) |
Design sign-off | 30 Oct 2026 | M2 30% |
UAT sign-off | 4 Dec 2026 | M3 30% |
Go-live and handover | 9–11 Dec 2026 | M4 10% |
Item | Amount (₹) |
Direct cost (BAC) | 4,58,000 |
Contingency reserve | 45,800 |
Cost baseline | 5,03,800 |
Management reserve | 22,900 |
Total project budget | 5,26,700 |
Signed for | Signature | Date |
Project Sponsor (Delivery Head) | Name and signature: ____________ | Date: ________ |
Project Manager | Name and signature: ____________ | Date: ________ |
WEB-2026-01/PCH · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.