Project Charter


Phase: Pre-sales and initiation | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Project Charter is the internal document that officially starts the project. It names the Project Manager, states the objectives and budget, and says how much authority the PM has.

Think of it like: It is like an appointment letter for the project: 'This project exists, here is the goal, here is the money, and you are in charge.'

When is it created?

Start of the project (5 Oct 2026)

Who prepares it?

Project Manager drafts it

Who approves or uses it?

Project Sponsor (Delivery Head)

What happens next?

Planning begins; the PM can now use company resources


How it connects to other documents

  1. Objectives are measured at the end in the Project Closure Report.
  2. The budget summary comes from the Project Budget.
  3. PM authority limits (₹10,000) are used in the Change Management Plan.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Formally authorises the project, names the Project Manager and states the objectives, budget and authority limits.

Item


Detail


Document no.

WEB-2026-01/PCH

Version

1.0

Date

5 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Pre-sales and initiation

Status

Approved


1. Project purpose

[Client Name] has awarded us a fixed-price contract to build its new corporate website. Delivering on time and within budget protects a 15.5% gross margin and positions us for a follow-on maintenance contract and a Hindi-language phase 2.


2. Objectives

#


Objective


Success measure


1

Deliver the agreed scope

All 7 SOW deliverables accepted by the client

2

Launch on time

Go-live on or before 9 Dec 2026

3

Stay within budget

Final cost within cost baseline of ₹5,03,800

4

Meet quality targets

No critical or high defects at launch; pages under 3 s on 4G

5

Satisfied client

Client satisfaction score of 4 or more out of 5 at closure


3. High-level scope

In scope: 10-page responsive WordPress website, contact form, blog, portfolio, analytics, on-page SEO, hosting setup, training and 14-day support. Out of scope: e-commerce, logins, integrations beyond the contact form, marketing, and maintenance after support ends.


4. Milestones

Milestone


Target date


Payment


Kickoff

5 Oct 2026

M1 30% (advance)

Design sign-off

30 Oct 2026

M2 30%

UAT sign-off

4 Dec 2026

M3 30%

Go-live and handover

9–11 Dec 2026

M4 10%


5. Budget summary

Item


Amount (₹)


Direct cost (BAC)

4,58,000

Contingency reserve

45,800

Cost baseline

5,03,800

Management reserve

22,900

Total project budget

5,26,700


6. Key risks

  1. Client content arriving late.
  2. Extra design revision rounds.
  3. Informal scope additions.
  4. Reduced capacity during Diwali week.


7. Project Manager authority

  1. Assign and schedule team members' work within approved hours.
  2. Approve changes and release contingency up to ₹10,000 per change.
  3. Approve timesheets and third-party purchases listed in the Procurement Plan.
  4. Escalate to the sponsor: any change above ₹10,000, any use of management reserve, or a forecast beyond the cost baseline.


8. Approval

Signed for


Signature


Date


Project Sponsor (Delivery Head)

Name and signature: ____________

Date: ________

Project Manager

Name and signature: ____________

Date: ________


WEB-2026-01/PCH · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. No charter, no official project: it gives the PM authority.
  2. Objectives must be measurable (dates, rupees, defect counts).
  3. It is short and high level; details go in the plans.


Common mistakes to avoid

  1. Objectives with no measure, such as 'deliver a good website'.
  2. Not stating the PM's approval limits.
  3. Treating the charter as a client document; this one is internal.


Next lesson: 11. Stakeholder Register