Phase: Planning | Audience: Internal | Project: WEB-2026-01 Corporate Website Development
In simple words: The Resource Plan shows who works on the project and for how many hours. The RACI Matrix shows, for each activity, who is Responsible (does it), Accountable (owns it), Consulted and Informed.
Think of it like: In a family function: one person cooks (Responsible), one person decides the menu (Accountable), grandma is asked for advice (Consulted), and neighbours are told the date (Informed).
When is it created? | Planning (9 Oct 2026) |
Who prepares it? | Project Manager |
Who approves or uses it? | Internal; shared with team |
What happens next? | Used to assign work and decide who approves what |
Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.
Issued by: [Your Company] Technologies Pvt. Ltd.
Purpose: Who works on the project, for how long, and who is Responsible, Accountable, Consulted or Informed for each key activity.
Item | Detail |
Document no. | WEB-2026-01/RAM |
Version | 1.0 |
Date | 9 Oct 2026 |
Owner | Project Manager |
Audience | Internal |
Phase | Planning |
Role | Hours | Active weeks | Average allocation |
Project Manager | 80 | 1–10 | 20% |
UI/UX Designer | 100 | 1–5 | 50% |
Frontend Developer | 160 | 3–10 | 50% |
Backend / CMS Developer | 120 | 1–10 | 30% |
QA Tester | 60 | 7–10 | 38% |
Content Writer | 40 | 1–8 | 13% |
Total | 560 |
R = Responsible (does the work), A = Accountable (owns the outcome, only one), C = Consulted, I = Informed.
Activity | PM | Designer | Frontend | Backend | QA | Content | Client Head of Mktg | Client Mktg Exec |
Requirements | A/R | C | C | C | I | I | C | R |
Sitemap | A | R | I | C | I | C | C | C |
Wireframes and designs | A | R | C | I | I | C | C | C |
Design approval | R | C | I | I | I | I | A | C |
Theme development | A | C | R | C | I | I | I | I |
CMS configuration | A | I | C | R | I | I | I | I |
Content supply | C | I | I | I | I | C | A | R |
Content upload and SEO | A | I | I | C | I | R | I | C |
System testing | A | I | C | C | R | I | I | I |
UAT | R | I | C | C | C | I | A | R |
Go-live decision | R | I | C | C | C | I | A | I |
Change request approval | R | I | C | C | I | I | A | C |
Training | A | I | I | R | I | I | I | C |
Note: Each row has exactly one A. When two people think they are both accountable, decisions stall; when nobody is, work gets dropped.
WEB-2026-01/RAM · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.