Resource Plan and RACI Matrix


Phase: Planning | Audience: Internal | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Resource Plan shows who works on the project and for how many hours. The RACI Matrix shows, for each activity, who is Responsible (does it), Accountable (owns it), Consulted and Informed.

Think of it like: In a family function: one person cooks (Responsible), one person decides the menu (Accountable), grandma is asked for advice (Consulted), and neighbours are told the date (Informed).


When is it created?

Planning (9 Oct 2026)

Who prepares it?

Project Manager

Who approves or uses it?

Internal; shared with team

What happens next?

Used to assign work and decide who approves what


How it connects to other documents

  1. Hours match the WBS and Budget.
  2. Approvers (A) sign the sign-off forms and Change Requests.
  3. Informed (I) people receive the Status Report.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Who works on the project, for how long, and who is Responsible, Accountable, Consulted or Informed for each key activity.


Item


Detail


Document no.

WEB-2026-01/RAM

Version

1.0

Date

9 Oct 2026

Owner

Project Manager

Audience

Internal

Phase

Planning


1. Resource plan

Role


Hours


Active weeks


Average allocation


Project Manager

80

1–10

20%

UI/UX Designer

100

1–5

50%

Frontend Developer

160

3–10

50%

Backend / CMS Developer

120

1–10

30%

QA Tester

60

7–10

38%

Content Writer

40

1–8

13%

Total

560




2. RACI matrix

R = Responsible (does the work), A = Accountable (owns the outcome, only one), C = Consulted, I = Informed.

Activity


PM


Designer


Frontend


Backend


QA


Content


Client Head of Mktg


Client Mktg Exec


Requirements

A/R

C

C

C

I

I

C

R

Sitemap

A

R

I

C

I

C

C

C

Wireframes and designs

A

R

C

I

I

C

C

C

Design approval

R

C

I

I

I

I

A

C

Theme development

A

C

R

C

I

I

I

I

CMS configuration

A

I

C

R

I

I

I

I

Content supply

C

I

I

I

I

C

A

R

Content upload and SEO

A

I

I

C

I

R

I

C

System testing

A

I

C

C

R

I

I

I

UAT

R

I

C

C

C

I

A

R

Go-live decision

R

I

C

C

C

I

A

I

Change request approval

R

I

C

C

I

I

A

C

Training

A

I

I

R

I

I

I

C


Note: Each row has exactly one A. When two people think they are both accountable, decisions stall; when nobody is, work gets dropped.

WEB-2026-01/RAM · v1.0 · Internal. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Exactly one 'A' per activity.
  2. The client can be Accountable for approvals like design and UAT.
  3. It removes confusion about who decides.


Common mistakes to avoid

  1. Two people both 'Accountable'.
  2. Nobody accountable for client content supply.
  3. Overloading one person across the peak weeks.


Next lesson: 19. Communication Plan