Design Sign-off Form


Phase: Execution | Audience: Shared | Project: WEB-2026-01 Corporate Website Development


Understand it first

In simple words: The Design Sign-off Form is the client's formal written approval of the final designs. After this, design changes become change requests, and the second payment (M2) can be invoiced.

Think of it like: Before a tailor cuts the cloth, you approve the final measurements and design. After that, changes cost extra.


When is it created?

End of design phase (30 Oct 2026)

Who prepares it?

Project Manager prepares it

Who approves or uses it?

Client Head of Marketing signs

What happens next?

Development starts; M2 invoice is raised


How it connects to other documents

  1. Completes deliverable D2 in the SOW.
  2. Triggers the M2 invoice in the Invoice Tracker.
  3. Later design changes go through the Change Request process.


The sample document

Below is the actual document for project WEB-2026-01. Read the purpose first, then go through each numbered section.

Issued by: [Your Company] Technologies Pvt. Ltd.

Purpose: Formal client approval of the final UI designs. Signing this form completes deliverable D2 and triggers the M2 invoice.


Item


Detail


Document no.

WEB-2026-01/DSO

Version

1.0

Date

30 Oct 2026

Owner

Project Manager

Audience

Shared with client

Phase

Execution

Status

Approved


1. Designs submitted

Design


Version


Desktop


Mobile


Home

v3

Approved

Approved

About Us

v2

Approved

Approved

Service page template

v2

Approved

Approved

Portfolio

v2

Approved

Approved

Blog listing

v2

Approved

Approved

Blog post

v2

Approved

Approved

Contact Us

v2

Approved

Approved


Design files: Figma project link [link]. Exported PDFs attached to the sign-off email of 28 Oct 2026.

2. Revision rounds

Round


Feedback received


Revised designs sent


1

21 Oct 2026

23 Oct 2026

2

26 Oct 2026

28 Oct 2026


3. Client comments at sign-off

Approved. Minor change to hero image crop to be handled during development, as agreed in the call of 29 Oct.


4. Declaration

I confirm that the designs listed above are approved for development. Changes after this sign-off will be handled through the change request process and may affect cost and schedule.

Signed for


Signature


Date


Head of Marketing, [Client Name]

Name and signature: ____________

Date: ________

Project Manager

Name and signature: ____________

Date: ________


WEB-2026-01/DSO · v1.0 · Shared with client. Bracketed items such as [Client Name] are placeholders.


Key takeaways

  1. Sign-offs protect both sides and trigger payments.
  2. Record how many revision rounds were used.
  3. Written approval is better than a verbal 'looks good'.


Common mistakes to avoid

  1. Starting development without signed approval.
  2. Not recording which version was approved.
  3. Forgetting to raise the invoice on the same day.